Notice: curl_setopt(): CURLOPT_SSL_VERIFYHOST no longer accepts the value 1, value 2 will be used instead in /home/admin/web/eastrussia.ru/public_html/gtranslate/gtranslate.php on line 101
Deputy Prime Minister Dmitry Rogozin will come to the Vostochny space center every two weeks - EastRussia |

Irkutsk
Ulan-Ude

Blagoveshchensk
Chita
Yakutsk

Birobidzhan
Vladivostok
Khabarovsk

Magadan
Yuzhno-Sakhalinsk

Anadyr
Petropavlovsk-
Kamchatsky
Moscow

This text is translated into Russian by google automatic human level neural machine.
EastRussia is not responsible for any mistakes in the translated text. Sorry for the inconvinience.
Please refer to the text in Russian as a source.

We are visited by the auditor

Vice-Premier Dmitry Rogozin will come to the spaceport Vostochny every two weeks

We are visited by the auditor

Deputy Prime Minister Dmitry Rogozin once again visited the main Far Eastern construction site. There are no fewer questions on the organization of work - the human factor is the basis of most problems.

Barrel of tar

A lot of booths, where red and blue are lagging behind the schedule, and people checking a distant and important object in the wilds of Amur forests - the vice-premier’s next visit to the Vostochny space center again began with reports, reconciliation of funding and plans. Despite the implacable statistics, the changes are obvious: the number of workers has increased since the end of February and the amount of work done has increased.

Now the main builders' forces are thrown on the creation of a force floor of the assembly and test complex of the launch vehicle (MIK PH): workers drill piles to a depth of 8 meters - a mark below the ground freezing level. This is necessary in order to withstand a cart with a rocket, the load on each wheel set of which will be more than 40 tons.

The work done is a spoon of honey in a barrel of tar: both TsENKI and Roskosmos are still unhappy.

“We are faced with the fact that, going according to temporary equipment installation schemes, we cannot guarantee its physical safety and good condition due to the cleanliness of the premises and what is happening there,” said Igor Komarov, head of the Roskosmos, to Rogozin. “In addition, by squeezing the time of installation of the equipment, we are depriving ourselves of time to refine and debug it.”

As it turned out, the builders themselves can become hostage to the work of a clumsy bureaucratic system. On other objects, the fact that some problems are still coming from the designers has surfaced again.

“We still have a number of premises for which the construction working documentation does not always correspond to the structures. Such changes to the documentation came after we had concreted the structures, ”explained Alexander Mordovets, first deputy director of Spetsstroy, to Rogozin. “As a result, we can hand them over for installation of equipment only by March 30.”

Sometimes the weather comes on. "We need to drill piles - well, I'll bury them in the frozen ground, and then they'll swim," continues Mordovets, "what's the use of this work?" And it takes time to warm up - hence the discrepancy with the schedule. "

Later it turned out that on the main and, as one would like to believe initially, illustrative construction, there is a place for the heroes of Krylov's fable about the swan, cancer and pike: at the most problematic site (the city of Tsiolkovsky) there are no obstacles in the construction plan.

“We had a supplier that“ flew off ”- at the time of the initial tenders, the plant for the production of the electrical cable worked quite well, and through 2 of the year went bankrupt, - explains a representative of Spetsstroytekhnologii. “We have found understanding with the customer, we want to order it at another enterprise, we have already agreed, and the designer again asks to redesign all the issues.”

"We sent two solutions for cable products to the customer's name - we have not received a response so far," was the answer of the project's chief engineer.

Or another: “We thought here, but what if the armature is knitted not with 0,7 wire, but with 0,8 - then it will be possible to save labor resources (you will have to knit less often) and materials. They wrote to the designer - we were not answered ... "

“In my opinion, it’s not at all the level of deputy chairman or director of Spetsstroy to decide what wire to knit reinforcement or which cable to lead,” Rogozin retorted sarcastically. - Only one conclusion: you do not have any communication on this object. It turns out that you do not interact at all. From now on, if you do not understand, representatives of the design institute must be constantly present here, who for some reason have been visiting here on a case-by-case basis, and I personally entrust the control of Tsiolkovsky to Alexander Volosov. ”



Work is in full swing

Despite all the shortcomings, the Vice Prime Minister noted that there are advantages on the East: for example, the government's instruction to create the headquarters of the launch site was fulfilled, and he immediately began to work effectively.

More than fifty people will literally live in the East up to putting objects into operation. Specialists on the ground level from the heads of departments to the heads of departments should monitor literally everything from preparation and execution of works to the movement of finance and interaction with subcontractors. There are six different units here.

"Today, as never before, the maximum coordination of all participants in the process is important. To do this, the headquarters of the Special Construction of Russia was created, the heads of the central apparatus, all the management of the enterprises subordinated to the Special Forces, were called up to take all the necessary administrative decisions here, "explains the deputy chief of the operational headquarters of the Spetsstroy of Russia for the construction of the spaceport Maksim Kryukov.

In round-the-clock mode, operational duty officers solve any issues arising at the construction site. For two weeks, worked more than a thousand calls. After all, the process of building the spaceport goes to the finish line.

“Constantly calls are received - more than a hundred per day. For example, somewhere we need to help with the machine, with a crane, we promptly react, transfer information to the necessary authorities, ”says Alexey Udovenko, the operational duty officer of the Special Construction Company of Russia.

In addition, the process of coordinating the as-built documentation with the customer has accelerated, ready-made premises are more quickly transferred to the equipment installation. With about a quarter of the work that was needed, Rogozin expressed confidence that they would be completed on time. It is necessary to adjust the coordination of all structures so that the 12 of the largest objects of the so-called “start-up minimum” are delivered on time. Due to the criticality of the moment, Rogozin said, the time has come for even tougher control measures. This should contribute not only to "measures of personal responsibility", but also stimulus ruble. More precisely, its withdrawal for the day of delay.

“First, I have demanded to concentrate here, on the East, all the human and financial resources of Spetsstroy in order to prevent backlog of schedules,” said the Deputy Prime Minister of Russia after a closed meeting. - Secondly, we plan to additionally consider the measures of personal, as well as the financial responsibility of Spetsstroy for each day of disruption of the construction site. These proposals will be presented to the Prime Minister and the President of the country. ”

Tomorrow on the East will be held the college of Spetsstroy, where detailed reports of all departments of the federal construction agency will be heard, schedules re-drawn up and instructions given. Of the important thing - the leaders of all spetsstroevsky Glaucks will gather at it, who will submit to Alexander Volosov proposals on states that they can allocate for work on space construction. The quality of work of the board Dmitry Rogozin promised to evaluate soon - 3 of April.