Notice: curl_setopt(): CURLOPT_SSL_VERIFYHOST no longer accepts the value 1, value 2 will be used instead in /home/admin/web/eastrussia.ru/public_html/gtranslate/gtranslate.php on line 101
Kuzbass investor has agreed to build access roads with Russian Railways - EastRussia |

Irkutsk
Ulan-Ude

Blagoveshchensk
Chita
Yakutsk

Birobidzhan
Vladivostok
Khabarovsk

Magadan
Yuzhno-Sakhalinsk

Anadyr
Petropavlovsk-
Kamchatsky
Moscow

This text is translated into Russian by google automatic human level neural machine.
EastRussia is not responsible for any mistakes in the translated text. Sorry for the inconvinience.
Please refer to the text in Russian as a source.

"Sukhodol" rises on the rails

Kuzbass investor has agreed to build access roads with Russian Railways

Photo: shutterstock.com
Special project Coal of the East of Russia
JSC "RZhD" in the person of its Far Eastern Railway has signed an agreement on the provision of services for joining the non-use routes of stevedore LLC "Sea Port" Sukhodol "to its infrastructure - from the future coal terminal in Shkotovskaya Bay to Smolyaninovo station. The Sukhodol MP, owned by the Siberian Business Union (SDS), the Kemerovo holding, plans to build the terminal in three stages - a capacity of 6 million tons, then 12 million tons and 20 million tons per year.

Stevedore plans that it will be able to ship up to 3,5 thousand tons of coal products per hour - the terminal of Daltransugol (SUEK structure) near Vanino possesses similar productivity in the Far East today. The capacity of the port of Suhodol will allow servicing ships with the maximum deadweight of 120 thousand tons. Two berths longer than 600 m and other facilities, in particular a warehouse with the area of ​​170 ha, will be available to it, which will allow 1,2 million tons of coal to be stored at a time. Investments in the project are estimated at more than 30 billion rubles.

Project port "Sukhodol" has a serious background. SDS said about it in 2012, having estimated investments in 18 billion rubles, and expected to introduce the first stage of the terminal in 2017 year. Then the Volga Group Gennady Timchenko entered the project in 2014 year, having bought 50% of the operator-operator of the future terminal from the VTS, but already in 2015 the structures of Mr. Timchenko left the project.

The construction of the coal terminal in Sukhodol Bay was considered suspended due to lack of funding from the SDS, but in the spring of 2018, it was resuscitated. LLC Sukhodol MP 18 May 2018 year was granted the status of a resident of the free port of Vladivostok with relying tax, customs and administrative preferences. Then the financial director of the company Olga Kornienko stated that "the terminal's design was completed and positive conclusions were obtained on the environmental and state expertise of Glavgosexpertiza not only on the port terminals, but also on the external infrastructure: railways and energy."

Since the project to create the port of Suhodol is not the first year, the plans of railroad workers to develop infrastructure in Primorye partly took into account the possibility of the emergence of this consignee. Currently, the Smolyaninovo station is undergoing a reconstruction. In addition to lengthening the existing and construction of additional receiving and sending routes, a park is planned separately, which will work with trains going to the direction of Smolyaninovo-Danube, including the following to new customers - in addition to Sukhodol, in the area of ​​Cape Open and the Bay of Defenseless, a coal port Vera with a capacity of up to 20 million tons per year. The contract of the port of Suhodol with the Far Eastern Road is endorsed within the framework of an investment agreement, previously concluded between RZD and SDS in the fields of the St. Petersburg International Economic Forum.

It is important for coal miners to guarantee future transport volumes in conditions of limited capacity of the public infrastructure. Here you can draw an analogy with UK Colmar, which is leading the development of coal deposits in the south of Yakutia. Due to RZhD's obligations to meet the growing needs of the company for export of its products, the issue of the reconstruction of one of the directions of the Neryungri-Bestuzhevo railway (Tynda), which was not initially included in the modernization program of the Baikal-Amur Mainline and the Trans-Siberian railway before 2020, has moved forward.

As noted in the stevedoring company, with the growing demand for Russian coal in the Asian market in the Far East, we will feel a shortage of specialized port facilities. At the same time, the transshipment complex in Sukhodol Bay should provide access to a new export channel to small and medium-sized coal-mining enterprises of Russia (among the shippers, in addition to JSC HC "SDS-Ugol", CJSC "Siberian Anthracite", OJSC "Russian Coal", LLC MC " Zarechnaya, ZAO Yenisei Industrial Company and others). Due to the future port, foreign supplies of Russian coal miners in value terms may increase by 70-84 billion rubles. annually in 2014 prices.



Coal is still one of the main export items through the Far Eastern ports, many of which (Daltransugol, Vostochny Port, Evraz NMPT, Posyet Trade Port) specialize precisely in this type of cargo. According to the Association of Russian Sea Commercial Ports, in the first half of the year 2018 cargo turnover of the ports of the Far East Basin increased to 98,2 million tons (by 2,3%), of which dry cargo grew to 61,1 million tons (5% growth), and bulk cargo decreased to 37 million tons (minus 1,7%). East processed 34,6 million tons, Vanino - 14,8 million tons, Nakhodka - 12,2 million tons, Poset - 3,7 million tons of cargo.

By 2020, the aggregate deficit in the capacity of the ports of the Far Eastern Federal District is estimated at 70 million tons per year, including 66,5 million tons per annum for bulk cargo and 3,5 million tons for grain cargo. The throughput of BAM and Transsib should grow by about 1,5 times in the coming years - up to 180 million tons per year.

The works financed by the federal budget and RZD within the framework of the program for the development of the Eastern landfill should be completed in 2019. Reconstruction will help the station to cope with the increased flow of train traffic. The task is to increase the throughput to 65 pairs of trains per day, now, on the average, this figure is 50 pairs. Meanwhile, this may not be enough in a few years.

Smolyaninovo today is focused mainly on the processing of cargo traffic in the direction of the ports of the Nakhodka Knot. Last year, over 60 million tons of cargo was delivered to them by rail. In the coming years, shipments may exceed 100 million tons. The increase will be due to the increase in existing port capacities and the emergence of new ones. In particular, JSC Vostochny Port is putting into operation an additional terminal, as a result, 600 wagons per day will be added to the existing car-stream.

One of the limiting areas for traffic growth will be the Shkotovo-Smolyaninovo Passage Pass. The movement of freight trains here is carried out with a pushing locomotive. To overtake does not become a barrier, on the Far Eastern road offer to build a more gently bypassed section of length about 29 km. Thus, there will be a reserve for the future, as it is expected that by the year of 2030 annual shipments to the Nakhodka-Vostochnaya and Khmylovsky ports can only grow to 116 million tons. However, the price of the issue is considerable. According to preliminary estimates, the construction of a bypass section Shkotovo-Smolyaninovo will cost at least 11,5 billion rubles.

In the case of a positive decision, this facility will be included in the program of the second stage of modernization of the Baikal-Amur Mainline and the Trans-Siberian Railway until 2026. The final decision on its implementation should be taken at the level of the government of the Russian Federation.