Notice: curl_setopt(): CURLOPT_SSL_VERIFYHOST no longer accepts the value 1, value 2 will be used instead in /home/admin/web/eastrussia.ru/public_html/gtranslate/gtranslate.php on line 101
DHA to send 824 million rubles for the reconstruction of the Sovetskaya Gavan heat supply system - EastRussia | News Khabarovsk Territory

Irkutsk
Ulan-Ude

Blagoveshchensk
Chita
Yakutsk

Birobidzhan
Vladivostok
Khabarovsk

Magadan
Yuzhno-Sakhalinsk

Anadyr
Petropavlovsk-
Kamchatsky
Moscow

This text is translated into Russian by google automatic human level neural machine.
EastRussia is not responsible for any mistakes in the translated text. Sorry for the inconvinience.
Please refer to the text in Russian as a source.

Warm investments

ДГК will allocate 824 million rubles for the reconstruction of the heat supply system of Sovetskaya Gavan

Warm investments
Photo: Yuri Smitiuk

JSC Far Eastern Generating Company (part of the RusHydro group) will send 824 million rubles to implement the investment program for the reconstruction of the heat supply system in the city of Sovetskaya Gavan (Khabarovsk Territory). The project implies the construction of six new central heating stations (TSC), a repair and maintenance base, a dispatch center, as well as intra-quarter heat networks. JSC "Khabarovsk Repair and Assembly Company" will be the general contractor.

The new TSCs and networks are the logical continuation of another project-TEC Sovetskaya Gavan, implemented by PJSC RusHydro. Within its framework, RusHydro is building a station and a heating main into the city.

The TPP in Sovetskaya Gavan is one of four projects of the investment program of PJSC RusHydro for the construction of new power facilities in the Far East, implemented in accordance with the Presidential Decree. The total amount of budget funds allocated by the state for the development of the basic branch of the economy - energy - in the Far East is 50 billion rubles. With this money, four priority heat generation facilities will be built: 1-Ya turn of Yakutsk SDPP-2, 1-second of Sakhalinskaya GRES-2, CHPP in Sovetskaya Gavan and 2-stage of Blagoveshchenskaya CHP.

The CHP in the city of Sovetskaya Gavan is designed to replace the retiring capacity of the technically obsolete Mayskaya GRES (Maisky settlement of the Khabarovsk Territory) operating at high fuel consumption. The construction of a new power plant will also allow the liquidation of a number of low-cost boiler houses in the city and thereby significantly improve the environmental situation.



The installed electric capacity of the first stage of the CHPP will be 120 MW, the heat output - 200 Gcal / h. Within the first stage, the construction of an in-site infrastructure for the next stages of the station with a total capacity of 360 MW will be completed. Urgalsky coal of "G" grade is supposed to be used as a fuel for the production of electricity and heat.

"In order for the new CHPP to supply heat and hot water to residents of the Soviet Harbor, it is necessary not only to build the station itself and the heating main to the city, but also to prepare the city's heat networks for the reception of this heat. Now municipal heating is provided by municipal heat. The project will allow to close inefficient boiler houses, providing centralized year-round heat supply of their consumers from the CHPP due to the construction of central heat points. It will be built 6 TSC, repair and maintenance base and control room, as well as laid 3,3 thousands of running meters of intra-quarter heat networks, "- said Deputy General Director for Capital Construction and Investment JSC" DGC "Maxim Nichlonsky.

Work on the implementation of the investment project of JSC "DGC" began in 2016 year. To date, the design of facilities has been completed, the documents have passed state expertise, a building permit has been obtained. In March of 2018, construction work should start. Completion of the project is planned in 2019 year.