Notice: curl_setopt(): CURLOPT_SSL_VERIFYHOST no longer accepts the value 1, value 2 will be used instead in /home/admin/web/eastrussia.ru/public_html/gtranslate/gtranslate.php on line 101
Thermal Power Plant in Sovetskaya Gavan: Energy for BAM - EastRussia |

Irkutsk
Ulan-Ude

Blagoveshchensk
Chita
Yakutsk

Birobidzhan
Vladivostok
Khabarovsk

Magadan
Yuzhno-Sakhalinsk

Anadyr
Petropavlovsk-
Kamchatsky
Moscow

This text is translated into Russian by google automatic human level neural machine.
EastRussia is not responsible for any mistakes in the translated text. Sorry for the inconvinience.
Please refer to the text in Russian as a source.

CHPP in Sovetskaya Gavan

Energy for BAM

CHPP in Sovetskaya Gavan

For residents of the port city of Sovetskaya Gavan, a new CHP is a window to the future. It was not just for a long time waited, these expectations here, without exaggeration, lived. Built in the 1935 year, the Mayskaya GRES has decayed and supplies electricity with disruptions. Electricity is kind of, but expensive, unreliable and in obvious deficit.

Now the situation is changing: in 2016, in the Sovetskaya Gavan, a new CHP will start operating. Design, registration of construction permits, preparation and coordination of documentation are close to completion. Part of the equipment has been delivered, part has been ordered. Preparation of the site and related infrastructure for the main stage of construction work has already begun: a highway and railway tracks are being built, along which the necessary equipment for construction will be delivered to the future power plant. Later the same route will deliver fuel. There is confidence: the deadlines will be met, the object will not be long-standing. After all, 80% of the main equipment of the new CHP has already been manufactured, and some of the units have been delivered to the construction site altogether. Preliminary work is funded by JSC RAO Energy Systems of the East. Construction at the expense of funds allocated under the targeted decree of the President of the country is conducted by JSC RusHydro.

First of all, the construction is aimed at ensuring the uninterrupted supply of electricity and heat to residential and industrial facilities of the Soviet-Havana and neighboring Vanino district.

“The development of the infrastructure of the port special economic zone, the construction of cargo terminals, industrial enterprises without reliable energy supply is impossible,” says the head of the Soviet-Gavansky district, Yuri Bukhryakov. “It’s impossible to give it to the outdated Mayskaya State District Power Plant, therefore, the construction of a new CHP is vital.”

Plans for the construction of industrial facilities in the Soviet Harbor are many: it is expected to build a multi-port and ship repair center, container and coal terminals, industries for fish and seafood processing. You can start these building projects only after the restrictions on the connection to the mains and heat are removed.

Construction of the station will finally solve the problem with the city's water supply. "Hot water is not a blessing, but a necessity for a normal life," says Pavel Borovsky, the mayor of Sovetskaya Gavan. "With the advent of the CHP, the townspeople will finally be able to use hot water all year round."