Notice: curl_setopt(): CURLOPT_SSL_VERIFYHOST no longer accepts the value 1, value 2 will be used instead in /home/admin/web/eastrussia.ru/public_html/gtranslate/gtranslate.php on line 101
JSC "Vostochny Port" informs about the beginning of commissioning of reloading equipment of the Third Stage - EastRussia | Far East

Irkutsk
Ulan-Ude

Blagoveshchensk
Chita
Yakutsk

Birobidzhan
Vladivostok
Khabarovsk

Magadan
Yuzhno-Sakhalinsk

Anadyr
Petropavlovsk-
Kamchatsky
Moscow

This text is translated into Russian by google automatic human level neural machine.
EastRussia is not responsible for any mistakes in the translated text. Sorry for the inconvinience.
Please refer to the text in Russian as a source.

JSC "Vostochny Port" informs about the beginning of commissioning of the reloading equipment of the Third Stage

The specialists of the "Eastern Port" together with representatives of the Japanese company Mitsui Miike and "Khabarovsk repair and assembly company" (the contractor who is installing the equipment at the Third stage) will connect each of the six machines (2 stacker and 4 reclaimer) to the power supply and check all Whether the mechanisms work properly.

JSC "Vostochny Port" informs about the beginning of commissioning of the reloading equipment of the Third Stage
At the moment, the specialists of the Japanese company-manufacturer of equipment Mitsui Miike have already arrived at the port, the company said. It is reported that a series of test launches of reclaimers and stackers is necessary for debugging the assembled equipment.

Now technical specialists are checking the correct response of the first reclaimer. While on the territory of the Third stage there are no own fixed electric networks, they use a mobile diesel generator with power 520 kVA.

It is reported that in the near future, "East Port" will complete the construction of the substation "Ugolnaya-2" 35 / 6 kilovolt with two transformers of 16 thousand KVA.