Notice: curl_setopt(): CURLOPT_SSL_VERIFYHOST no longer accepts the value 1, value 2 will be used instead in /home/admin/web/eastrussia.ru/public_html/gtranslate/gtranslate.php on line 101
Russian and Chinese energy specialists held a meeting on the operation of the Amurskaya-Heihe interstate transmission line - EastRussia | Far East

Irkutsk
Ulan-Ude

Blagoveshchensk
Chita
Yakutsk

Birobidzhan
Vladivostok
Khabarovsk

Magadan
Yuzhno-Sakhalinsk

Anadyr
Petropavlovsk-
Kamchatsky
Moscow

This text is translated into Russian by google automatic human level neural machine.
EastRussia is not responsible for any mistakes in the translated text. Sorry for the inconvinience.
Please refer to the text in Russian as a source.

Power engineers of the Russian Federation and the People's Republic of China held a meeting on the work of the interstate power line Amurskaya - Heihe

The power engineers of the Russian Federation and the People's Republic of China held a meeting on the operational dispatch management of the joint operation of the Unified Energy System of Russia and the power system of China on the interstate 500 kV Amur-Heihe transmission line. It is reported by the press service of the System Operator of the UES of Russia.

The meeting, which took place in Khabarovsk, was attended by representatives of the Unified Energy System of East OJSC and the Northeast Dispatch and Communications Center of the State Electric Grid Corporation (HES) of China.

“During the meeting, it was possible to reach agreements on resolving issues of improving interaction between the dispatch centers of the ODU of the East and the Northeastern VAC GEC of China under the joint management of the interstate 500 kV Amurskaya-Heihe line. The implementation of the decisions made will contribute to improving the reliability of this interstate line, ”Natalya Kuznetsova, chief dispatcher for the ODE of the East, commented on the results of the meeting. The meeting participants also tentatively agreed on the dates for the joint emergency response control training on the Amurskaya-Heihe line management. It is scheduled for the second half of August - early September 2014 of the year.

According to SO UES, in 2013, 3495 million kW / h of electricity was supplied to the PRC along all Russian-Chinese interstate transmission lines. The largest volume of exports - 2208 million kW / h - is carried out through the Amur - Heihe line.