Notice: curl_setopt(): CURLOPT_SSL_VERIFYHOST no longer accepts the value 1, value 2 will be used instead in /home/admin/web/eastrussia.ru/public_html/gtranslate/gtranslate.php on line 101
For the reconstruction of coastal structures in the port of Vanino Rosmorport will send 2019 billion rubles to 1 - EastRussia | Far East

Irkutsk
Ulan-Ude

Blagoveshchensk
Chita
Yakutsk

Birobidzhan
Vladivostok
Khabarovsk

Magadan
Yuzhno-Sakhalinsk

Anadyr
Petropavlovsk-
Kamchatsky
Moscow

This text is translated into Russian by google automatic human level neural machine.
EastRussia is not responsible for any mistakes in the translated text. Sorry for the inconvinience.
Please refer to the text in Russian as a source.

For the reconstruction of coastal structures in the port of Vanino Rosmorport will send 2019 billion rubles to 1

Rosmorport will complete the reconstruction of onshore structures of the Vanino-Kholmsk auto-rail ferry in the Vanino seaport in 2018 year

For the reconstruction of coastal structures in the port of Vanino Rosmorport will send 2019 billion rubles to 1
This was announced by Leonid Terebizh, director of the FSUE "Rosmorport" Vanino branch.

The work is estimated at 1 billion rubles. They are held within the framework of the federal target program "Economic and social development of the Far East and Baikal region for the period up to 2018 year", as well as in connection with the construction of a new ferry project CNF11CPD.

In particular, it is proposed to extend the two berths, install new breakers and mooring bollards. In addition, it is planned to reconstruct the span structures of the lifting and transition bridges taking into account the passage of heavy-duty road trains.

It is also planned to install a Ro-Ro type vessel on the bridge for the ferry of the CNF11CPD project and operating ferries of the Sakhalin type, Interfax notes.

The works will be conducted in two stages - alternately at two berths. "Reconstruction will be carried out in the conditions of the port and one of the lines of the ferry crossing," L. Terebizh specified.

According to him, the bulk of the work is scheduled for 2017-2018 years, The draft will be prepared by the Vladivostok PrimorProektBureau. A tender to determine a contractor is scheduled for the end of 2016 of the year - the beginning of 2017 of the year.