Notice: curl_setopt(): CURLOPT_SSL_VERIFYHOST no longer accepts the value 1, value 2 will be used instead in /home/admin/web/eastrussia.ru/public_html/gtranslate/gtranslate.php on line 101
A new substation for the region’s largest ski base will be built by Kamchatskenergo - EastRussia | Far East

Irkutsk
Ulan-Ude

Blagoveshchensk
Chita
Yakutsk

Birobidzhan
Vladivostok
Khabarovsk

Magadan
Yuzhno-Sakhalinsk

Anadyr
Petropavlovsk-
Kamchatsky
Moscow

This text is translated into Russian by google automatic human level neural machine.
EastRussia is not responsible for any mistakes in the translated text. Sorry for the inconvinience.
Please refer to the text in Russian as a source.

The new substation for the largest ski area in the region will be built by Kamchatskenergo

The construction of a substation in the city of Elizovo, Kamchatsky Krai, for the supply of the region's largest mountain skiing base Moroznaya starts Kamchatskenergo (part of the holding company of RAO ES of the East)

A new substation for the region’s largest ski base will be built
"The cost of construction is 191,5 million rubles. The object is planned to be built before the end of 2016, "the report says.

Substation "Frosty" is one of the projects of the investment program "Kamchatskenergo" in 2016 year.

“The substation will give impetus to the development of infrastructure on Mount Moroznaya, in the area of ​​which the base of the same name is located, which should become the first modern ski resort in Kamchatka. The ability to connect to networks will increase the investment attractiveness of the site, which will give impetus to the creation of new ski facilities (lifts, snow cannons, lighting, etc.) and new facilities in the service sector (hotels, catering, etc.) ", - emphasize in the power company.

In addition, the possibility of a new substation 35 / 10 kV "Moroznaya" will allow to provide technological connection to the electric networks of new consumers in the territory of Yelizovo, and also to increase the reliability of the power supply system of this city.

“The preparatory stage of work has already been completed on the territory of the future substation. Contracting specialists started the installation of reinforced concrete foundations for the placement of the main equipment - two power transformers and closed switchgears 35 kV and 10 kV in block-modular design, ”the press service notes.

The bulk of the construction and installation work is scheduled for May and June 2016, when most of the ordered equipment and materials will arrive on the peninsula. In the same period, work will begin on laying two cable lines 10 kV (length 5,2 km each) from the new substation to the ski base.