Notice: curl_setopt(): CURLOPT_SSL_VERIFYHOST no longer accepts the value 1, value 2 will be used instead in /home/admin/web/eastrussia.ru/public_html/gtranslate/gtranslate.php on line 101
Transfer of Yakutskaya GRES-2 input to 2017 year was confirmed by RusHydro - EastRussia | Far East

Irkutsk
Ulan-Ude

Blagoveshchensk
Chita
Yakutsk

Birobidzhan
Vladivostok
Khabarovsk

Magadan
Yuzhno-Sakhalinsk

Anadyr
Petropavlovsk-
Kamchatsky
Moscow

This text is translated into Russian by google automatic human level neural machine.
EastRussia is not responsible for any mistakes in the translated text. Sorry for the inconvinience.
Please refer to the text in Russian as a source.

Transfer of input of the Yakutsk state district power station-2 to 2017 year was confirmed by RusHydro

In the first half of the year 2017 plans to put into operation Yakutskaya GRES-2 RusHydro, the company's head Nikolai Shulginov told reporters on Friday in Yakutsk

Transfer of input of the Yakutsk state district power station-2 to 2017 year was confirmed by RusHydro
"Despite the increase in the pace of construction, I believe that in the complete completed form the object will not be handed over this year," the head of RusHydro said.

Answering the question whether the object will be commissioned in the first quarter of 2017, he said: “No, rather, in the first half of the year”.
"The lag is due to harsh conditions. The first delays occurred already at the beginning of construction and were associated with the dismantling of the pile field. And also there were delays with design estimates, "the head of the company specified.

Yakut GRES-2 (first stage) is one of four projects of the RusHydro investment program for the construction of new power facilities in the Far East, implemented jointly with RAO ES of the East. The electric power of the first stage of the new station is 193 MW, thermal power is 469 Gcal.h (taking into account the peak hot-water boiler).

The launch of the first stage of the Yakutsk SDPP-2 was originally planned in 2015 year, the date was fixed in the contract of general contracting, which was concluded with the "TEK Mosenergo". The limiting estimated cost of construction of the Yakutsk SDPP-2 in accordance with the conclusion of the FAU "Glavgosexpertiza of Russia" - 26,2 billion rubles, Interfax notes.

In February 2016, Sergey Tolstoguzov, General Director of RAO "ES of the East", told journalists that the construction and assembly works within the first stage of the Yakutsk SDPP-2 will be completed on time, the station will be loaded at the end of October 2016.

At the same time, Deputy Prime Minister of the Russian Federation, presidential envoy to the Far East Yuri Trutnev said that he was not entirely satisfied with the answer of the company "RusHydro" for the construction of the facility. "I had a question - will they succeed or not? The answer did not suit me completely. But overall the work is on - and I hope that by the end of the year all problems will be solved and the station will be put into operation, "Trutnev said. He acknowledged that RusHydro faced "the slovenliness of suppliers who believe that the supply of equipment can somehow be considered in the light of sanctions."

In May of this year, the construction customer - Yakutskaya GRES-2 JSC (a subsidiary of PJSC RusHydro, located in the trust management of PJSC RAO ES of the East) - noted the backlog in the work of the general contractor of TEK Mosenergo. In particular, this was due to the insufficient number of staff.

The Ministry of Energy of the Russian Federation intends to strengthen control over the construction progress of the Yakutsk TPP-2 in order to prevent the postponement of commissioning of the facility.