Notice: curl_setopt(): CURLOPT_SSL_VERIFYHOST no longer accepts the value 1, value 2 will be used instead in /home/admin/web/eastrussia.ru/public_html/gtranslate/gtranslate.php on line 101
The berth for the Amursky GPP is almost half built - EastRussia | Far East

Irkutsk
Ulan-Ude

Blagoveshchensk
Chita
Yakutsk

Birobidzhan
Vladivostok
Khabarovsk

Magadan
Yuzhno-Sakhalinsk

Anadyr
Petropavlovsk-
Kamchatsky
Moscow

This text is translated into Russian by google automatic human level neural machine.
EastRussia is not responsible for any mistakes in the translated text. Sorry for the inconvinience.
Please refer to the text in Russian as a source.

The berth for the Amursky GPP is almost half built

The berth for the Amursky GPP is almost half built
The temporary berth for the Amur Gas Processing Plant (Amursky GPP) is built at 40%, the company said.
A temporary dock is being built on the Zeya River, and the contractor is Tres Zapsibgidrostroy. By November 28, 235 tons of steel structures have already been installed, and a total of 1,04 thousand tons of steel structures will be installed at the facility for the construction of a berth wall with a length of 125 meters.


During the construction of the Amur GPP, the equipment will be delivered by barge-towed trains, which will proceed from the port of Sovetskaya Gavan upstream of the Amur and Zeya rivers to the construction site of hydraulic structures.


At the next stage of the construction of the berth for the GPP, facilities will be built on the bank of the river: a platform for the installation of cranes, warehouses and parking. Along with this, "Trust Zapsibgidrostroy" performs work on dredging.


The berthing capacities are designed for cargo turnover up to 32 thousand tons and are designed for unloading and intermediate storage of large and heavy equipment. Designed facilities should provide unloading of equipment with a mass of one place up to 1,2 thousand tons. By October next year, construction is scheduled to be completed.