Notice: curl_setopt(): CURLOPT_SSL_VERIFYHOST no longer accepts the value 1, value 2 will be used instead in /home/admin/web/eastrussia.ru/public_html/gtranslate/gtranslate.php on line 101
The project of the new city water intake of Yakutsk will go on state examination not earlier than December - EastRussia | Far East

Irkutsk
Ulan-Ude

Blagoveshchensk
Chita
Yakutsk

Birobidzhan
Vladivostok
Khabarovsk

Magadan
Yuzhno-Sakhalinsk

Anadyr
Petropavlovsk-
Kamchatsky
Moscow

This text is translated into Russian by google automatic human level neural machine.
EastRussia is not responsible for any mistakes in the translated text. Sorry for the inconvinience.
Please refer to the text in Russian as a source.

The project of the new city water intake of Yakutsk will be submitted to the state examination not earlier than December

At the end of October, the question arose about the quality of drinking water in Yakutsk - a new urban water intake

The project of the new city water intake of Yakutsk will be submitted to the state examination not earlier than December
As already reported by IA "EastRussia", experts of Rospotrebnadzor have revealed Organoleptic changes in tap water in Yakutsk in connection with the seasonal decrease in the water level in the Lena River.

“Design of water intake continues. The delays (receipt of the conclusion of the state examination was scheduled for October) occurred due to its rise in price. After all, originally imported equipment was laid. The designer (CJSC Stroyproekt Institute (St. Petersburg) - IF) has been tasked with reducing the cost to the cost of import substitution as much as possible without sacrificing quality, ”said Gavril Levin, First Deputy Minister of Housing and Public Utilities and Energy of Yakutia.

The water intake in Yakutsk was built in 1970 year. Initially, its water supply capacity was 35 thousand cubic meters. Meters per day. After the reconstruction, the capacity was brought to 60 thousand cubic meters per day. The existing water intake does not have treatment plants, but only disinfects facilities.

Gavril Levin stressed that in the fall, preparatory work was carried out to secure the site and deliver the main equipment. At the end of November, excavation works are planned, which should be performed exactly in winter time: “In this regard, the customer is working on the issue without waiting for the release of design work,” Interfax reports.

“It is not expected to raise the cost of the project. Now the designer lets all his strength to meet the limits of the construction limit. The project will be handed over to the state expert examination by the end of the year, most likely in December, ”G. Levin added.
As reported, in May this year, the representative of the general contractor Tahal Consulting Engineers Ltd. Alexander Dubov noted that design and survey works are being carried out at the site, and the state expertise conclusion will be received in September-October of the year 2015, after which construction and installation works will start.

He also specified that the whole complex with treatment facilities and reagent facilities will be delivered in the second quarter of 2018.

At the end of October 2014, Tahal Consulting Engineers Ltd. won the tender of Vodokanal to choose the general contractor for the construction of a new water intake in Yakutsk. The total cost of the project was 3,9 billion rubles, the winning company reduced the cost to 3,6 billion rubles. In early December, the general contractor and the customer signed a contract. According to the terms of the tender, 1 thousand 220 days are allocated for water intake, and 1 thousand days for the sewage treatment plant. The capacity of the new water intake will be 110 thousand cubic meters. meters per day.