Notice: curl_setopt(): CURLOPT_SSL_VERIFYHOST no longer accepts the value 1, value 2 will be used instead in /home/admin/web/eastrussia.ru/public_html/gtranslate/gtranslate.php on line 101
The cost of construction of Far Eastern stations now amounts to 88 billion rubles - EastRussia | Far East

Irkutsk
Ulan-Ude

Blagoveshchensk
Chita
Yakutsk

Birobidzhan
Vladivostok
Khabarovsk

Magadan
Yuzhno-Sakhalinsk

Anadyr
Petropavlovsk-
Kamchatsky
Moscow

This text is translated into Russian by google automatic human level neural machine.
EastRussia is not responsible for any mistakes in the translated text. Sorry for the inconvinience.
Please refer to the text in Russian as a source.

The cost of construction of Far Eastern stations now amounts to 88 billion rubles

RusHydro increased the cost of construction of Far Eastern stations to 88 billion rubles

The cost of construction of Far Eastern stations now amounts to 88 billion rubles
PJSC RusHydro will sign an additional agreement to the contract with the Federal Property Management Agency and the Energy Ministry on new parameters for the construction of four stations in the Far East, their new marginal cost is estimated at 87,8 billion rubles, the company said.

Earlier, the company estimated the total cost of construction of the first stage of the Sakhalin TPP-2, the first stage of the Yakutsk TPP-2, the second stage of the Blagoveshchenskaya TPP and the TPP in Sovgavani at 63 billion rubles, Interfax reports.

According to the new parameters of the projects - CHP in Sovetskaya Gavan at the maximum estimated cost of the facility in accordance with the conclusion of the FAU "Glavgosexpertiza of Russia" 18,6 billion rubles. will be put into operation in 2017 year with an input capacity of 120 / 200 MW / Gcal.

Sakhalinskaya GRES-2 (1-I queue) - 34,8 - 2017 - 120 / 18,2; Yakut State District Power Station-2 (1-I queue) - 26,2 - 2016 - 193,48 / 469,6; Blagoveshchenskaya CHP (2-I queue) - 8,2 - 2015 - 120 / 188, respectively.

As explained in the company, the company previously calculated the marginal cost based on similar projects. Now, however, it was recalculated based on the results of the development of design and estimate documentation, the conclusion of the State Expert Review and an independent technological and price audit.

The draft agreement has already been agreed in the Ministry of Energy and Rosimushchestvo, the company notes.
As reported, for the construction of four stations previously allocated 50 billion rubles. from the budget.