Notice: curl_setopt(): CURLOPT_SSL_VERIFYHOST no longer accepts the value 1, value 2 will be used instead in /home/admin/web/eastrussia.ru/public_html/gtranslate/gtranslate.php on line 101
Issues of infrastructure development of the Mikhailovsky TOR were discussed in Primorye - EastRussia | Far East

Irkutsk
Ulan-Ude

Blagoveshchensk
Chita
Yakutsk

Birobidzhan
Vladivostok
Khabarovsk

Magadan
Yuzhno-Sakhalinsk

Anadyr
Petropavlovsk-
Kamchatsky
Moscow

This text is translated into Russian by google automatic human level neural machine.
EastRussia is not responsible for any mistakes in the translated text. Sorry for the inconvinience.
Please refer to the text in Russian as a source.

The issues of infrastructure development of the Mikhailovsky TOR discussed in Primorye

The Governor of the Primorsky Territory, Vladimir Miklushevsky, today, 21 July, during a working visit to the Mikhailovsky district held a meeting on the development of the infrastructure of the advanced development Mikhailovsky. At the meeting, the date was announced for the start of the construction of the first facility of the largest resident of the TOP

The issues of infrastructure development of the Mikhailovsky TOR discussed in Primorye
During the meeting, representatives of relevant departments of the Administration of the Territory, as well as resource-supplying organizations reported on the implementation of measures to ensure the infrastructure of the TOR site, the press service of the regional government said.

According to the director of the Department of Transport and Road Management, Alexander Shvory, the beginning of the construction of the Mikhailovka-Turiy Rog-Nekruglovo highway on 0:2,5 kilometers is scheduled for this fall. Project documentation and engineering survey results have already been submitted for state expert review.

Andrei Boyko, Deputy Director of the Corporation for the Development of the Far East, reported on the progress in the implementation of measures for the electricity supply of the facility.

“The construction of four substations is planned. It is planned to hand over the first two DRSK 30 on August 2017 of the year, two more - in December of the next year, ”he said.

Work on the construction of water supply facilities is planned to begin already at the beginning of 2017. According to Elena Parkhomenko, the Deputy Director of the Department for Housing and Fuel Resources and Fuel Resources, the project of territory planning will be ready in the near future.

According to the energy department of the region, Gazprom has already submitted project documentation for the construction of two gas distribution stations to the state examination. For inter-settlement gas pipelines, amendments will have to be made to the regional state program.
Vladimir Miklushevsky stressed that the plans of all participants in the implementation of the territory of advanced development should be synchronized and clearly implemented.

"This implies project management: every link is important in the chain. If we make roads, but do not bring electricity, the TOP will not work, and vice versa. Sergei Petrovich, your task as a leader is to coordinate the whole process and make decisions on emerging issues. Moreover, every week it is necessary to conduct operational meetings on project implementation, "the head of the region said.

And about. Director of the Department of Project Management of the Territory, Alexander Shubin added that at present, summary plans for the execution of infrastructural works are being prepared.

In parallel with the provision of the TOR infrastructure, August 1, the largest resident, LLC RusAgro Primorye, is ready to begin construction of the first facility.

"We plan to go to the site 1 August. This will be a block of foundations for the elevator complex, so that in the next year first grain elevators can take corn grain of our farmers. The rest of the objects will begin to be sold in 2017 year ", - Dmitry Podkidyshev, General Director of OOO Rusagro-Primorye, said.

Also, according to him, according to the three first pig complexes, the project documentation is already under examination, in the middle of August, equipment is expected to be delivered, 5 September - the beginning of construction.

Recall, the top Mikhailovsky specializes in the production of agricultural products. There will be two largest pork production complexes. The company "Mercy Trade" builds complexes with the simultaneous content of 700 thousand pigs. The second resident is RusAgro Primorje, a subsidiary of the largest Russian agro-holding. It builds production complexes with the simultaneous content of 540 thousand pigs.

According to Vladimir Miklushevsky, these are tens of billions of rubles of investments in the production of an export-oriented product. The plans of the regional authorities are to increase the production of pork at 12 times, which exceeds the need of Primorye residents. Therefore, meat will be supplied to China.