Notice: curl_setopt(): CURLOPT_SSL_VERIFYHOST no longer accepts the value 1, value 2 will be used instead in /home/admin/web/eastrussia.ru/public_html/gtranslate/gtranslate.php on line 101
Construction of fuel and energy facilities in the Far East corresponds to construction schedules - Chamber of Accounts - EastRussia | Far East

Irkutsk
Ulan-Ude

Blagoveshchensk
Chita
Yakutsk

Birobidzhan
Vladivostok
Khabarovsk

Magadan
Yuzhno-Sakhalinsk

Anadyr
Petropavlovsk-
Kamchatsky
Moscow

This text is translated into Russian by google automatic human level neural machine.
EastRussia is not responsible for any mistakes in the translated text. Sorry for the inconvinience.
Please refer to the text in Russian as a source.

The construction of fuel and energy complex in the Far East corresponds to the construction schedule - the Chamber of Accounts

The Accounting Chamber of the Russian Federation has considered the results of monitoring the implementation of priority projects of the fuel and energy complex of Eastern Siberia and the Far East by the public joint-stock company "Federal Hydro-Generating Company - RusHydro"

The construction of fuel and energy complex in the Far East corresponds to the construction schedule - the Chamber of Accounts
The Board of the Accounts Chamber of the Russian Federation, chaired by Tatyana Golikova, reviewed the results of monitoring the implementation of priority projects of the fuel and energy complex of Eastern Siberia and the Far East by the public joint-stock company Federal Hydrogenerating Company - RusHydro (construction of a CHP plant in Sovetskaya Gavan, Sakhalinskaya GRES-2 (1-I Turn), Yakutsk SDPP-2 (1-I turn), Blagoveshchenskaya CHP (2-I turn).

The Accounts Chamber quarterly reports on the results of the ongoing monitoring of the activities of PJSC RusHydro in accordance with the instructions of the State Duma of the Russian Federation, the press service of the RF JV reported.

Objects of inspection: the Ministry of Energy of the Russian Federation, the Ministry of Economic Development of the Russian Federation, Public Joint-Stock Company Federal Hydrogenerating Company - RusHydro, as well as Public Joint-Stock Company Sberbank of Russia.

The study period: IV quarter 2015

A report was made by the auditor Valery Bogomolov.

As of 1 in January, 2016 has allocated 38 billion rubles to finance the construction of energy facilities from all sources. Including due to budget investments 32,9 bln. Rub. Mastered a total of - 23,5 billion rubles. In the authorized capitals of subsidiaries RusHydro sent 43,9 billion rubles. or 87,8% of allocated budget investments.
As of 1 in January, 2016 was in deposits of PJSC RusHydro and S & A * there were 17,1 billion rubles. - 34,2% of investments received for construction. The amount of interest received from the placement of funds was from 2013 to 2015. - 12,8 billion rubles.

Separately, the auditor dwelled on the construction of Blagoveshchenskaya CHP.

In October, 2015 was the adjustment of the project part of the object and set the stages of construction. The completion date of the first stage is 2015, the second stage is May 2016.

As the auditor noted, the first stage of construction was completed in 2015 year. In December 2015, a comprehensive testing of the equipment was carried out and, in accordance with the Urban Development Code, the necessary documents were submitted for obtaining permission to commission the first stage of the Blagoveshchenskaya CHPP. Permission for commissioning was received 21 January 2016. In January, 2016, the facility was put into operation in design parameters: 120 Megawat electric and 188 Gigacallium of heat output. "However, the agreement on provision of budgetary investments does not provide for the phased introduction of the facility into operation. The contract provides for the introduction of the facility in 2015, "- explained Valery Bogomolov.

The Board noted the need to bring into compliance with the Agreement on the provision of budgetary investments, taking into account the phasing of the Blagoveshchensk CHP.

Within the second phase of the construction of the Blagoveshchenskaya CHP, construction of a cooling tower, roads, as well as landscaping and landscaping of the territory is envisaged. The deadline for completing the second stage in the spring of this year.

Earlier, the Accounts Chamber reported problems with the general designer of the Е4 Group at the CHP plant in Sovetskaya Gavan, the termination of the contract occurred in October 2015 of the year. “According to the results of the competitive procedures, an agreement was concluded in January of this year on the development of working documentation for the construction of a heat and power plant in the town of Sovetskaya Gavan with Lonas Technology JSC. The deadline for the development of the main part of the working documentation is no later than 30 in June of 2016. Completion of the work on the development of working documentation is not later than 20 in February of 2017, ”said the auditor.

The construction of the Yakutsk SDPP-2 and Sakhalinskaya GRES-2 is being carried out by the general contractor of the TEK Mosenergo in accordance with the calendar-network schedules.

During the discussion of the construction site of the Yakutsk TPP-2, the auditors raised the question of the readiness of heating networks in connection with the commissioning of the TPP-2 capacities, and therefore the Board decided to seek the position of the Government of the Sakha Republic (Yakutia) and the administration of Yakutsk. And also send a request to the Federal Antimonopoly Service on measures taken to optimize tariff regulation due to changes in the scheme of participants in the processes of power generation, heat generation and transportation of thermal energy, due to the commissioning of GRES-2 power plants in the Republic of Sakha (Yakutia).

The college decided to send an information letter to the Deputy Prime Minister - Plenipotentiary Representative of the President of the Russian Federation in the Far Eastern Federal District, as well as a report to the chambers of the Federal Assembly.